Tender bid submission procedure – details and instructions

Submitting a bid as part of the tender process must follow the requirements outlined in the official tender documentation and involves the preparation of three separate folders:

1. Application File (Dosarul Cererii)

2. Technical Offer File (Dosarul Ofertei Tehnice)

3. Financial Offer File (Dosarul Ofertei Financiare)

1. Application File

The Application File must include:

• An official covering letter, drafted according to Annex No. 1, signed by the investor or their authorized representative.

• The application form, following the format in Annex No. 2, which contains general information about the investor and demonstrates compliance with eligibility criteria.

• The bid guarantee, formatted as per Annex No. 5, submitted either as a scanned document or electronically signed file. The original must be presented on the day of bid opening.

Additional attachments:

• A copy of the company’s registration certificate.

• A self-declaration confirming the absence of insolvency or liquidation procedures.

• Technical documentation that proves compliance with the qualification criteria.

• A detailed index of the offer, listing all documents and the number of pages for each (a table of contents is recommended).

These documents may be submitted either as one consolidated and digitally signed PDF or as separate signed PDFs. Regardless of the format, each file must be clearly labeled and well organized. The bid guarantee, as it is signed by a third party (bank), must be submitted as a separate file.

2. Archiving and File Transfer

The Technical and Financial Offer files must be archived separately using 7-zip to ensure confidentiality and data integrity.

If the total file size exceeds 20 MB, it is recommended to use a secure file-sharing platform (e.g., Google Drive, Dropbox) and send the download link to the tendering authority to ensure proper access and processing.

3. Presentation at the Opening Session

On the day of the bid opening session (April 1st), the investor’s representative must present a valid ID and the original authorization (power of attorney) confirming their right to represent the investor.

spot_imgspot_img
spot_img
spot_img
spot_img

ȘTIRI RECENTE

Moldova se apropie de 1 GW din regenerabile și își depășește înainte de termen țintele pentru 2030

Ne apropiem de 1 GW de energie regenerabilă instalată în Republica Moldova, iar dinamica...

Studiu ANRE despre piața energiei electrice în 2025: cum arată de fapt concurența, dependența de import și viitorul CET-urilor

Agenția Națională pentru Reglementare în Energetică a finalizat studiul de piață referitoare la sectorul...

How Vladislav Papanaga sees smart energy as the next big asset class

For Vladislav Papanaga, antrepreneur and founder of QGroup, energy is no longer just one...

Vladislav Papanaga: Energia inteligentă — noul standard de diversificare a afacerilor

Autor: Vladislav Papanaga, antreprenor, fondator QGroup Deficitul energetic ca fereastră de oportunitate Energia nu este doar...

SIMILARE

How Vladislav Papanaga sees smart energy as the next big asset class

For Vladislav Papanaga, antrepreneur and founder of QGroup, energy is no longer just one...

Vladislav Papanaga: Energia inteligentă — noul standard de diversificare a afacerilor

Autor: Vladislav Papanaga, antreprenor, fondator QGroup Deficitul energetic ca fereastră de oportunitate Energia nu este doar...

ODA va finanța companiile care intră în comunități de energie regenerabilă

Mâine se aprobă proiectul de hotărâre a Guvernului privind semnarea Acordului de grant pentru...

Ministerul Energiei: Doi oameni noi în Comisia pentru licitațiile eoliene

Ministerul Energiei a completat, în sfârșit, locurile rezervate societății civile în Comisia de licitații...

Grid-forming obligatoriu pentru stocarea de energie și regenerabilele de peste 1 MW în Europa

Europa se pregătește să schimbe regulile jocului pentru stocarea de energie și pentru centralele...

Ministerul Energiei lansează două proiecte de regulamente pentru controlul încălzirii și ventilării în clădiri

Ministerul Energiei a pornit, în aceeași zi, două inițiative care vor schimba felul în...

LEA Vulcănești–Chișinău: șantierul se închide, linia intră în faza de testare și energizare treptată

Lucrările la Linia Electrică Aeriană (LEA) Vulcănești–Chișinău ajung la aproximativ 99% progres fizic. Constructorul...

We’ve launched Moldova’s first comprehensive digital map of renewable energy generation assets

RENERGY announces the launch of the first comprehensive digital map that consolidates all major...

Cel mai mare parc fotovoltaic propriu al Simtel, de 52 MWp la Giurgiu, intră în exploatare săptămâna aceasta

Simtel deschide, la Giurgiu, un nou capitol în povestea energiei regenerabile din România: cel...